March 2025 Update
• ROOF CURB INSTALLATION IS COMPLETE.
• BRICK VENEER INSTALLATION IS IN PROGRESS.
• INTERIOR DRYWALL INSTALLATION IS IN PROGRESS.
• MECHANICAL, ELECTRICAL, AND PLUMBING OVERHEAD ROUGH-IN IS IN PROGRESS.
• RTU INSTALLATIONS ARE SCHEDULED TO BEGIN SOON.