Feb. 2025 Update
• AREAS A AND B STRUCTURAL STEEL ERECTION, JOIST, AND DECKING WORK ARE IN PROGRESS.
• AREAS A AND B INTERIOR FRAMING INSTALLATIONS ARE IN PROGRESS.
• AREAS C IN-WALL PLUMBING AND ELECTRICAL ROUGH-INS ARE IN PROGRESS.
• AREA C ROOF WORK IS IN PROGRESS.
• AREAS A AND B FIRE SPRINKLER INSTALLATIONS ARE IN PROGRESS.
• AREA A, EXISTING ONE-STORY, 12” CONCRETE MASONRY UNIT FIREWALL INSTALLATION IS IN PROGRESS.
• EXTERIOR BRICK VENEER SCAFFOLDING ERECTION IS IN PROGRESS.
• EXTERIOR WALL WATERPROOFING AND INSULATION INSTALLATION ARE IN PROGRESS.