March 2025 Update
• COURTYARD CONCRETE POUR IS COMPLETE.
• AREAS B AND C BRICK VENEER INSTALLATION IS IN PROGRESS.
• AREAS B AND C TAPE AND BED IS IN PROGRESS.
• AREAS A AND B ROOFING WORK IS IN PROGRESS.
• AREA B STAGE FORMING IS IN PROGRESS.
• FIRE ALARM WIRE PULLING IS IN PROGRESS.
• RTU INSTALLATIONS ARE SCHEDULED TO BEGIN SOON.