April 2025 Update
• AREA C ROOFING WORK IS COMPLETE.
• NEW GAS LINE INSTALLATION IS COMPLETE.
• AREAS A AND B BRICK INSTALLATION IS IN PROGRESS.
• AREA B TAPE AND BED IS IN PROGRESS.
• AREA C STORM SHELTER WINDOWS AND FEMA LOUVER INSTALLATIONS ARE IN PROGRESS.
• DETENTION POND EXCAVATION AND GRADING ARE IN PROGRESS.
• AREA A ROOFING WORK IS IN PROGRESS.
• AREAS A AND B ALUMINUM WINDOW AND GLASS INSTALLATIONS ARE IN PROGRESS.