top of page
June 2025 Update
• AREAS B AND C’S SECOND COAT OF PAINT ARE COMPLETE.
• EXTERIOR BUILDING LETTER INSTALLATIONS ARE COMPLETE.
• BRICK VENEER INSTALLATION IS NEARING COMPLETION.
• AREA B’S TAPE AND BED IS IN PROGRESS.
• AREA C’S FLOORING AND CASEWORK INSTALLATIONS ARE IN PROGRESS.
• AREAS A AND B’S ALUMINUM STOREFRONTS/WINDOW INSTALLATIONS ARE IN PROGRESS.
bottom of page







