August 2025 Update

• SOD AND SEEDING INSTALLATIONS ARE COMPLETE.
• TEMPORARY IRRIGATION INSTALLATIONS ARE COMPLETE.
• THEATRICAL LIGHTS AND AV LOW-VOLTAGE WIRE INSTALLATIONS ARE NEARING COMPLETION.
• STAGE STEP INSTALLATIONS ARE SCHEDULED TO BEGIN SOON.
• SERVING LINE WORK IS COMPLETE.
• DISHWASHER DUCTWORK INSTALLATION IS NEARING COMPLETION.
• MISCELLANEOUS EQUIPMENT ATTACHMENT INSTALLATIONS ARE IN PROGRESS.
• WALK-IN COOLER/FREEZER CONDENSATE LINE INSTALLATION IS SCHEDULED TO BEGIN SOON.
• METAL WALL PANEL INSTALLATION IS IN PROGRESS.
• STAGE EQUIPMENT COMMISSIONING IS SCHEDULED TO BEGIN SOON.
• SERVICE GATES AND LOUVER INSTALLATIONS ARE SCHEDULED TO BEGIN SOON.